Key Insight: Existence Ocean Design Condos reports significant construction progress for June 2026, with Tower A's preliminary works and foundation now 100% complete.
For Tower A, preliminary works, including site clearing, layout, leveling, and excavation, are 100% concluded. The foundation work, encompassing continuous footings and foundation tie beams, is also 100% complete. The first level structure has reached a 25% physical advance, with columns, reinforced concrete beams, and initial steel work for girders underway. First level masonry, specifically block walls, shows an 18% physical advance.
Tower B's preliminary works are 90% complete, covering initial site activities and excavation. Foundation work for Tower B is at a 10% advance, with concrete templates and initial steel reinforcement for footings in progress.
Regarding installations, the wastewater treatment plant construction has reached a 60% advance. The process for converting to underground CFE medium voltage electrical lines is 50% complete.
Key Insight: Only 5 units remain available across the Existence development, with 28 units sold and 3 units reserved.
In Torre A, 2 units are available (A-12 at $402,189 and A-52 at $604,000), and 2 units are reserved. In Torre B, 3 units are available (B-12 at $402,189, B-13 at $435,402, and B-21 at $420,478), and 1 unit is reserved. The remaining available units are priced from $402,189 to $604,000.
Key Insight: A total of 8 units remain available across Existence Torre A and Torre B.
Supporting Details:
Key Insight: Only 8 units remain available across Existence Towers A and B.
4 units are available in Torre A (A-11, A-12, A-13, A-52) and 4 in Torre B (B-11, B-12, B-13, B-21). Prices for available units range from $402,189 to $435,402. A total of 28 units are now sold or reserved across both towers.
Key Insight: Construction for Condominios Existence, located in Zona Hotelera Sur, Cozumel Q. Roo, is scheduled from February 1, 2026, to December 31, 2027.
Torre A construction commences in February 2026, with preliminary work (Feb-Mar 2026), foundation (Apr-May 2026), and structure (Jun 2026-Jan 2027). Finishes are scheduled from August 2026 to October 2027.
Torre B construction is set to begin in July 2026, with preliminary work (Jul-Aug 2026), foundation (Sep-Oct 2026), and structure (Nov 2026-Jun 2027). Finishes are scheduled from January 2027 to December 2027.

Tired of the seasonal sargasso unpredictability on the mainland? Explore our curated selection of Cozumel luxury condos and pre-construction beachfront villas. As the only major destination in the Mexican Caribbean with a protected, sargasso-free west coast, Cozumel is no longer just a cruise port—it is the ultimate "climate-resilient" investment. Secure your footprint on the island’s pristine "Gold Coast" and capitalize on the limited land supply of Mexico’s largest inhabited island.